M.E.T.T.S. logo

M.E.T.T.S. - Consulting Engineers > Technical Innovations and Project Proposals > Bataan Nuclear Power Station Conversion Options

Options for the Conversion of the Bataan Nuclear Power Plant to Fossil Fuel Firing

 
Dr. Michael C. Clarke, Director, M.E.T.T.S. Pty. Ltd., Sydney, Australia

Mr. Douglas R. Ebeling, Associate, M.E.T.T.S. Pty. Ltd., Sydney, Australia

Eng. Donato L. Cordero, Engineering Manager, Bataan Nuclear Power Plant


(The following Executive Summary of a major report formed the basis of a paper presented at the 1st Philippine Conference on Energy Efficiency and Demand-side Management, Manila, January 1995.)

Capital costs and power generation costs are summarised in Table 1, for one coal conversion option, and the conversion of the plant to natural gas fired, combined cycle operation. For comparison purposes figures are also presented for the refurbishment, commissioning and running the plant as a nuclear power station.

Electricity costs from nuclear operation are considerably cheaper than for either the two conversion options. If power costs was the only criteria for operating the plant then nuclear firing would clearly win.

Both coal and natural gas conversions will have environmental consequences for the region. By the installation of best available technology and the application of best available practice, the impact will be minimised. The cost of technology and practice however will increase the cost of electricity produced by the plant.

Table 1. SUMMARY TABLE, FOSSIL FUEL CONVERSION OPTIONS, BNPP
- Revision, March 1995

 CONVERSION TO COAL CONVERSION TO N. GAS NUCLEAR COMPARISON
POWER OUTPUT MW(e) 800 1700  620
ENERGY OUTPUT GWH 5,600 (With FGD - 5400) 12,200 4,613
CAPITAL COST $USm 750 (With FGD - 1070) 1385 380 (UPGRADE)
Electricity Cost ¢US/kWH 4.82 (With FGD - 5.94)  5.24, 4.34 (FP $230/170) 3.50
Electricity Cost P/kWH 1.21 (With FGD - 1.49) 1.31, 1.09 (FP $230/170) 0.88
CAP. COST/POWER OUT 0.94 (With FGD - 1.34) 0.81 0.61
CONSTRUCTION TIME 42 MONTHS 42 18.24

FGD Flue Gas Desulphurisation (+ Selective Catalytic Reduction)
FP Fuel Price, Natural Gas ($US230 /tonne for LNG, $US170 /tonne piped gas) - (Coal $US 55 / tonne)


Notes on Table 1

For comparison purposes, the two fossil fuel conversion options and the nuclear comparison have each had the electricity cost based on a pay-back period of twenty years. In each case (for the table) it has been assumed that the full capital cost has been borrowed.

When financing packages are being considered, different pay-back periods are likely to be used. The periods are likely to increase with increasing debt. With the natural gas conversion option, an equity contribution would probably be included, since a BOT financing scheme may be used, that ties gas production, reticulation and use into one commercial package.

The electricity costs for coal and natural gas conversion are based on a reasonably optimistic scenarios, where no excessive ancillary capital works are charged against the plant. If environmental or other factors require such works, then increase in the electricity cost would occur. It is further considered that the plant required for conversion would be sourced from low cost countries; China, India, Australia, the Philippines etc, as far as possible. The costings for conversion are further premised on the use of the site allocated for construction of PNPP 2, in that it is supplied at no cost, and is geologically stable.

If the time required for the construction and commissioning is crucial, then the upgrading of the plant as a nuclear station is clearly the preferred choice. Further, the financial analyses indicate that the nuclear firing of the plant offers the cheapest electricity. Given that the nuclear fuel price is likely to remain stable over the foreseeable future (as against likely rises for coal and natural gas), the nuclear upgrading# and operation offers greater financial certainty to investors.

# M.E.T.T.S.'s estimate for upgrading the nuclear plant to 1997/8 standards is $US380m. It is backed by further external assessment, and includes new safety features. $US300m is the cost of a basic upgrading based on calculations carried out by the National Power Corporation.


SUMMARY - COAL FIRING

The conversion of the PNPP I plant to coal firing has some advantages. Coal technology is well proven, and only a small variation in the normal use of that technology is required to convert the plant. The power station will have a capacity similar to the design capacity for the nuclear plant, and will not be the largest plant in the new echelon of Luzon's power facilities. The plant of 800 MW(e) capacity will be relatively inexpensive at a capital cost of $US505m - without Flue Gas Desulphurisation, Selective Catalytic Reduction, or excessive expenditure on coal or ash handling and ignoring the previous expenditure on the nuclear system. A construction and commissioning period of 42 months is envisaged.

The coal option however offers unique co-economic opportunities. The ash waste product would be valuable if used in ancillary industry. By using the Lahar produced by the Pinatubo eruption as an aggregate, with the ash, iron oxide and cement, valuable building materials could be produced.

The disadvantages include designing and fitting an environmentally acceptable coal fired power station into the Bataan region. The materials handling alone will create many environmental, management and operational difficulties. The infrastructure requirements for materials handling will also raise engineering and environmental questions that will need to be solved before construction begins. Other environmental questions concerning emission reduction and control must also be answered before work can commence.

Another major disadvantage is the requirement for premium fuel, that is expensive in 1994, and in all probability will become relatively more expensive as the demand for 'clean' coal increases in the future.


SUMMARY - NATURAL GAS FIRING (COMBINED CYCLE, GAS TURBINE)

Natural gas provides the cleanest option for the conversion of the Bataan power station to fossil fuel firing. It further offers the most flexible power output to the grid. Options exist for running a part (or whole) of the plant as a single cycle peak load provider, or running the whole plant as a base load facility.

The environmental hazard that would be created by such a plant is low compared to coal. Thermal pollution to the sea would be greater than the nuclear option, in that if a 1700MW(e) plant was built with 46% efficiency, the waste heat would be 2000MW(t). This heat would be partially dissipated into the atmosphere (250MW) as against to the sea (1750MW). The additional heat discharge to the sea would be about 500MW(t).

NOx emissions can be successfully controlled by modern technology. Steam or water injection, ammonia addition or innovative combustion designs will produce acceptable (but not zero) NOx emissions.

At 1700MW(e), the power station would be the largest in the Philippines, and would certainly require a review of the Luzon energy plan. The total consumption of natural gas over a twenty five year period would be 2.5 TCF; over half the entire Philippine projected resource from Palawan. Over a billion dollars in capital would be needed to build the plant, plus an additional substantial sum to supply the fuel; either as LNG or pipeline gas.

The security of a large gas holding area would need to be addressed. Such a holding area and power station would make a relatively easy target when compared to a coal fired plant with coal yards or nuclear facilities.

The installation of the gas turbines could be achieved in eighteen months, but the construction of the steam generators and carrying out modifications to the existing plant would take a further twenty four months.

From the preliminary financial analysis, the construction of a new combined cycle power station makes better financial sense.


A NUCLEAR COMPARISON

Under the four headings (Technology, The Environment, Social and Political Concerns, and Economy) that were used to examine the coal-conversion option, a brief summary has been made of the nuclear option for comparison purposes.


Technology

Light water reactors are a very common type of nuclear reactor. They have good safety records, and most have high capacity factors. There development has been continuous, with technology now being available from Japan, Korea, France, the United Kingdom as well as the United States. They are used in close proximity to the Philippines (Japan, Korea and Taiwan) and have been earmarked for use in Indonesia and Malaysia.

The Bataan unit is 1970/80's technology. It is however essentially the same as new units, and could be readily upgraded to 1990's standards.

The Environment

The reactor will produce thermal pollution (waste heat) that will be disposed of, off Napot Point to the South China Sea. An environmental impact assessment cleared the plant for its designed heat disposal, and found that localised heating of the sea would not be excessive, given the strong currents that would ensure dispersion of the hot water.

No other polluting emissions could be expected from the nuclear power plant.

(Accidental emissions of radioactive material, are most unlikely. Once the plant was upgraded to 1997 standards, one accident in a million years could be expected.)

Social and Political Concerns

The perceived problems at the Bataan power plant are its greatest liability. These problems include seismic instability, claims of faulty workmanship and the lack of experience of the operators. Many geological and seismic inspections have been carried out on the site, with the result being that no significant risk is apparent. To convince Philippine Society of the seismic safety of the plant, an educational programme would need to be carried out that emphasised the sites stability, and the high seismic safety factor of the plant (0.4g).

Part of the process of refurbishment and upgrading, would be quality assurance on all systems and components of the plant. Modern QA techniques would need to be used to provide the certainty that all significant parts of the plant meet the highest safety and operational standards.
Initially foreign experts would be needed to run the plant. The retraining of Philippine staff would take considerable time and money, with the retrained staff spending a number of years assisting in operating similar plants in neighbouring countries.

Economics

By comparison with the costs of conversion to coal or natural gas, the refurbishment and upgrading of the plant for nuclear operation would be significantly cheaper. A maximum price of $US300m (including staff training) is a fair limit, compared to fossil fuel conversion alternatives.
The nuclear option should have the shortest lag time in terms of upgrading and commissioning. If foreign staff were used to initially man the plant then a period of eighteen to twenty months would be needed for full operation. This relatively short period, may be valuable in that the some of the expensive, old or temporary oil fired power plant could be retired early.
Fuel costs, plus operation and management costs for LWRs should cost no more than ¢US 2/kWH (0.54 Centavos/kWH). If the interest on the $US 300m was 12%, with a pay-back period of twenty years for the capital, then a further 0.9¢US/kWH would be added to the power cost. The total power cost would be 2.9¢US/kWH (0.78 Centavos/kWH).
If consideration was given to running the Bataan power station as a nuclear plant, then the environmental and economic benefits (as well as safety) should be emphasised, to overcome social and political opposition.


THE PHILIPPINES AND THE NUCLEAR CYCLE

The Philippines would be an importer of nuclear fuel and an exporter of spent fuel. The fuel that the reactor would use would be lightly enriched. As the uranium 235 is consumed, some plutonium is formed, part of which is also used up as fuel.

The spent fuel rods contain a depleted amount of uranium 235, a little plutonium but mostly non-fissile uranium 238. These fuel rods can be reused in heavy water type reactors (CANDU) that are running in Japan, Korea and Taiwan, as primary fuel. All the wastes would be processed by those countries, whilst the Philippines would receive a financial return for its used nuclear fuel. This is a win-win situation.

The sale of the used fuel rods could bring the net production cost of electricity (fuel plus operations and management) to under ¢US 1.5/kWH.


PLANT SECURITY AND THE NUCLEAR OPTION

Unfortunately there is an ongoing insurgency situation in the Philippines. The insurgency problems are no longer major, and in all probability will recede. All major plant however does need a security system. The Bataan plant was constructed with good external, perimeter and internal security systems.
There are commonly perceived notions that Nuclear Plants are susceptible to terrorist attack. These notions are based on a lack of understanding of the compact nature of nuclear plants, and the presence of very considerable containment structures for the reactor and fuel stores - especially American designed LWRs. The plant is easy to guard, and would be able to resist attack with light weapons, including rocket propelled grenades etc. The damage from such an attack would be limited to the knocking out of ancillary plant and structures, including the transformer yard, the auxiliary fuel tanks and administration building.


Notes

1. The above power cost figures are based on 1997 projected fuel prices, 12% interest, 85% availability, and 20 years amortisation.. The price of coal and natural gas are considered to be more liable for major increases, than nuclear fuel. The Asian demand for both coal and gas is expected to outstrip supply in the coming decade.

2. The estimated construction time includes planning and design, equipment construction, site modification, plant erection and commissioning, and staff training (coal and natural gas conversion). If major ancillary works are required (eg. major wharves, ash and coal pipelines, shipping channels etc), then both an increase in the construction time and costs could be expected.


NOTE:
You are welcome to quote up to a maximum of three paragraphs from the above paper, on condition that you include attribution to this website, as follows:
SOURCE: M.E.T.T.S. Pty. Ltd. Website http://www.metts.com.au


Search this Website:

M.E.T.T.S. HOME

COMPANY PROFILE

RESEARCH AND DEVELOPMENT PROJECTS
Radiant Tube Technology
Biodegradable Ordnance
Wastes Processing & Management
Spontaneous Combustion of Coal

TECHNICAL INVESTIGATIONS & PROJECT PROPOSALS
Bataan Nuclear Reactor: Conversion Options to Fossil Fuel
Conversion of Oil Fired Power Stations to Coal
Solid Waste Combustion with Power Generation
Gas-to-Liquids with Power Co-Production

WHITE PAPERS
NEW! Helium: Next Mineral to Boom in Australia?
Energy Security in Australia
Low Rank Coal/Lignite Upgrading Technologies
Cleaning UCG Synthesis Gas
GTL and CTL: New Energy Resources for Australia
Lignite: A New, Dedicated Approach
Carbon Capture and Storage
Power Generation Systems & Reliable Supply
LNG Carbon Footprints and CDM
Hybrid VAM and Coal Waste Fired Power Generation
Clean Coal Technology & Enhanced Oil Recovery

UCG-CSM Interrelationships and Synergies
Business Continuity Management and the Terrorist Threat
The Missing Link in Clean Coal Technology
The Realities of Solutions to the Energy Question
Energy for and from the Northern Territory (Australia)
Countering Terrorism Using Risk Management Tools
Engineering and Terrorism
Desalination and Power Generation
Full List of White Papers

PERSONNEL

CONTACT US


M.E.T.T.S. Pty. Ltd. - Consulting Engineers
PO Box 843, Helensvale QLD 4212, Australia
TEL: (07) 5502 8093 • (Int'l) +61-7-5502 8093
EMAIL: metts[at]metts.com.au


CopyrightPrivacyTerms of Use
© 1999-2014 M.E.T.T.S. Pty. Ltd. All Rights Reserved.

.